Sample Questions For PRINCE2-Foundation Exam
Question No : 1
Which is a purpose of quality planning?
A. Define the structure of the project management team
B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
C. Document approval records for those project products that have met their quality criteria
D. Produce the Project Plan with resource and schedule information
Answer: B
Question No : 2
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
A. Directing a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Managing Product Delivery
Answer: B
Question No : 3
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 aretrue
D. Neither 1 or 2 are true
Answer: B
PRINCE2-Foundation Exam
Study Material - PRINCE2-Foundation Exam Dumps Realexamdumps.com
Question No : 4
Which is a true statement about management stages and technical stages?
A. Technical stages can overlap but management stages CANNOT
B. Management stages are the responsibility of the Project Manager, technical stages are NOT
C. Technical stages create products, management stages do NOT
D. Management stages require quality control, technical stages do NOT
Answer: A
Question No : 5
What process provides the information required to decide whether to authorize the delivery of a project?
A. Directing a Project
B. Initiating a Project
C. Managing Product Delivery
D. Starting up a Project
Answer: B
Question No : 6
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience
Answer: B
Question No : 7
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
A. Those with a financial interest in the project
B. Those who will manage the project on a day-to-day basis
C. Those who will specify the desired outputs of the project
D. Those who will create the project's outputs
Answer: B
Question No : 8
Which should be funded by a change budget?
A. Increase in agreedscope
B. Increase in agreed scope
C. Increase in agreed scope
D. Handover activities
Answer: A
Question No : 9
Which is a task of product-based planning?
A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts
Answer: B
Question No : 10
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
A. Onlycorporate or programme management
B. Only the Project Board
C. Only the Project Manager
D. All levels of management
Answer: D