Sample Questions For PRINCE2-Practitioner Exam
Question No : 1
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes,systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period. Initial estimates indicated that the project would cost £2.5m and take two years to complete. MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years. The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs. Which 2 statements should be recorded under the Major risks heading?
A. Due to market conditions a suitable service provider may not be found, possibly leading to premature closure of the project.
B. Owing to employment contract changes staff may resist outsourcing, which would make it difficult to transfer staff to the selected service provider.
C. MFH's operations may be reduced and the 1a-year contract may not achieve its estimated value of £80m, which would reduce the service provider's profit.
D. The initial estimates, taken from the feasibility study report, indicate that the project will take two years to complete, which means that the business problems would remain for this period.
E. The management stages recommended by the consultants may not be appropriate,resulting in confusion in planning.
Answer: B,D
Question No : 2
Which of the following principles describes this statement?" xxx defines tolerances for each project objective to establish limits of delegated authority"
A. Manage by stages
B. Focus on products
C. Manage by exception
D. Learn from experience
Answer: C
Question No : 3
Which of the following reports does not contain any information on risk?
A. Issue Report
B. Highlight report
C. Lessons Report
D. End Stage Report
Answer: A
PRINCE2-Practitioner Dumps
Questions - PRINCE2-Practitioner Exam Braindumps Realexamdumps.com
Question No : 4
While planning the initiation stage, the Project Manager reviewed some threats that had been recorded in the Daily Log. Which threat should have been assessed for possible risk responses to be included in the Initiation Stage Plan?
A. MFH has no experience in outsourcing and this may affect understanding of what is required, resulting in inadequate plans and strategies.
B. The Project Brief is a complex document and may not be approved by the Executive.
C. There is a shortage of service providers so there is a possibility that no suitable service providers respond to the request for proposals. This would prevent the Outsourcing project from proceeding.
Answer: C
Question No : 5
Which other management product is created when the Business case is updated during Initiating a Project?
A. Post project review plan
B. Risk Register
C. Benefits Review plan
D. Issue Register
Answer: C
Question No : 6
Which project controls should be established for the Outsourcing project?
A. Highlight Reports to the Project Manager; Exception Reports to the Project Board when project tolerances are forecast to be exceeded.
B. Highlight Reports to the Project Board; Exception Reports to corporate management when stage tolerances are forecast to be exceeded.
C. Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or project tolerances are forecast to be exceeded.
Answer: C
Question No : 7
Which of the following statements is FALSE regarding the Continued Business Justification?
A. The justification for the project must remain the same throughout the project.
B. The justification for the project should remain vabd.
C. The justification for the project may change.
D. If the project is no longer justified it should be stopped.
Answer: B
Question No : 8
Additional Information

Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides
computer hardware to all business functions but has little awareness of the needs of his
colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards. Which 2 alternative actions apply to the proposed Senior Supplier for this project?
A. Retain because she is responsible for the design of the future Information Technology organization and working practices.
B. Add 'Director of Facilities' because he is responsible for the design of the future organization, processes, systems and operation models for Facilities.
C. Add 'Hardware Manager' because he provides computer hardware to all business functions and will be impacted by the outcome.
D. Remove because she only represents the Information Technology Division.
E. Replace with 'Director of Facilities' because he supports the initiative and has many ideas about how to improve the service.
Answer: A,B
Question No : 9
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services. MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which statement applies to the Quality standards section?
A. Delete entry 4 because external suppliers are responsible for applying any relevant standards to their work.
B. Delete entry 5 because the lack of a change management procedure makes the MFH document standards unsuitable.
C. Add 'All contracts must conform to current employment laws".
D. Add 'PRINCE2 change control procedures will be used to manage any changes to baselined products'.
Answer: C
Question No : 10
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management. All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair. Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,version and variant.
8. Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
The service level agreement looks like any other MFH document.
A. Obtain agreement from the Director of Facilities Division to redesign the service level agreement within the remaining +2 days tolerance.
B. Raise an issue (off-specification).
C. Accept this error as a concession.
D. No action required.
Answer: D